ROADS EPC CONTRACTDELIVERED 2024
Northern Bypass Agra Pavement Package
Agra Bypass Junction, Uttar Pradesh
MoRTH (Ministry of Road Transport and Highways)
CONTRACT VALUE
₹23 Cr
EXECUTION STATUS
COMPLETED
PROJECT CATEGORY
ROADS
GOVERNING AUTHORITY
MoRTH (Ministry of Road Transport and Highways)
PROJECT EXECUTIVE SUMMARY
High-speed 4-lane divided bypass pavement package executing high-performance bituminous layers, Dense Bituminous Macadam (DBM), Bituminous Concrete (BC), and heavy junction grade-separators connecting National Highway corridors.
KEY EXECUTION DELIVERABLES
Over 28,000 Metric Tonnes of high-specification bituminous mix laid and compacted
Achieved superior international roughness index (IRI < 1.8 m/km) across the corridor
Paved shoulders with rumble strips and retroreflective solar road studs
High-durability thermoplastic road markings and crash barrier installations
TECHNICAL SCOPE & METHODOLOGY
01.Application of cationic bitumen emulsion prime coat and tack coat with automated pressure sprayers
02.Laying of Dense Bituminous Macadam (DBM) with VG-40 bitumen to 100mm thickness
03.Laying of Bituminous Concrete (BC) wearing course using Crumb Rubber Modified Bitumen (CRMB-55)
04.Median construction, reinforced precast kerb stones, and paved shoulder drainage
QUANTITATIVE METRICS
Carriageway Length
14 Lane KM
Bituminous Mix
28,000 MT
Roughness Index
IRI < 1.8 m/km
Delivery Year
2024
EQUIPMENT & FLEET DEPLOYED
- 1 Vögele Super 1800-3 Hydrostatic Asphalt Sensor Paver
- 2 Tandem Vibratory Steel Compactors (HAMM HD 90)
- 1 Pneumatic Tyre Roller (PTR 24 Ton HAMM)
- 1 Insulated Bitumen Pressure Distributor (6,000 L)
- 16 Insulated Tipper Trucks
ENGINEERING CODES OF PRACTICE
- MoRTH Specifications for Road and Bridge Works Section 500 (Bituminous Works)
- IRC:37-2018 (Guidelines for Design of Flexible Pavements)
- IRC:SP:84-2019 (Manual of Specifications and Standards for Four Laning)